Hosting a Physical Server at the ADC

Summary

Customers submit a Service Request, Ethics Agreement, and ADC Web Request Form.
The IT Partner gathers documents and secures Change Request approval.
OPS reviews requirements, confirms capacity, and coordinates cabinet placement.
Network/IP setup is prepared, and the server is installed and documented.
Customer verifies connectivity, after which OPS closes the request.

Body

Procedure: Hosting a Server at the ADC

This document outlines the required steps for hosting a server at the Academic Data Center (ADC). The process involves actions from both the Customer and the Operations (OPS) Team.


Steps for the Customer

  1. Submit a Service Request (SR) Form
    • Log in to My Service Center and complete the Service Request Form.
    • Provide all required details, including:
      • Server make and model
      • Serial number
      • Number of network connections
      • Deployment deadlines
    • For the Server Location field, select ADC.
  2. Review and Sign the Ethics Agreement
  3. Submit the ADC Web Request Form
    • Complete the ADC-specific request form with the following details:
      • Intended server use and purpose
      • Application names
      • Operating system type
      • Any additional relevant information
    • The Data Center Operations Team will review this form.

Steps for the IT Partner Team

Change Request

  • The IT Partner will work with the customer to gather all required paperwork outlined in “Steps for the Customer” and submit the Change Request for approval. The request should include a coordinated time/date agreed upon by OPS and NMG.
  • Note: The IT Partner must provide all required documents and obtain the necessary approvals before proceeding with the deployment.

Steps for the Operations (OPS) Team

  1. Review Customer Submission
    • Verify all details provided in the SR and ADC Web Request Form.
  2. Check Requirements
    • Confirm server specifications and dimensions.
    • Validate network and power requirements.
  3. Validate Data Center Capacity
    • Ensure sufficient space, power, and network resources are available in the ADC.
  4. Confirm Network & Cabinet Location
    • Coordinate with Wayn M. or NMG to confirm cabinet placement and network readiness.
  5. Coordinate Equipment Delivery
    • Follow up with the customer on the expected arrival date of the equipment.
  6. Assign Equipment Naming
    • Generate server and device names in accordance with the UTHSCSA naming convention.
  7. Prepare Network Infrastructure
    • Submit a task for NMG to pre-run copper and fiber connections (data and management). Include:
      • Cabinet Number
      • Slot Number
      • Cassette/Patch Panel Number   
    • Obtain and assign the required IP addresses.
  8. Schedule Installation
    • Update the OPS calendar with the date and time for equipment installation in the ADC.
    Update Documentation
    • Update the rack elevation diagram.
    • Record the server details in the CMDB.
  9. Customer Configuration & Verification
    • Schedule a follow-up session for the customer to configure the assigned IPs.
    • Verify network connectivity and system availability in the new environment.
  10. Close the Request
    • Document the completed steps and close out the Service Request.

 